Road Rehab is nearing its 2017 goal of resurfacing 44 miles of City streets! Starting the week of August 21, construction on major arterial roads will take place at night, between the hours of 7:00 p.m. and 5:00 a.m. This is done to avoid interrupting the morning traffic flow.
Contractors will be monitoring noise level, to ensure local neighborhoods are not disrupted.
For work that is done during the day on streets near schools, construction will take place between 9:00 a.m. and 2:00 p.m. to accommodate school schedules. Contactors are also coordinating with each school to ensure bell schedules and school bus routes are not interrupted.
See the current status and upcoming plans for Copper Hill Drive and Wiley Canyon Road below:
Copper Hill Drive
- Digouts and grinding: Wed., August 16-Thur., August 17
- Leveling: Friday, August 18
- Paving: Monday, August 21-Tuesday, August 22
Wiley Canyon Road
- Digouts: Completed on Tuesday, August 15
- Grinding: TBD
- Paving: TBD
In addition to weekly City Brief updates, residents can now receive Road Rehab news by following the City of Santa Clarita’s Twitter account (@santaclarita). Unexpected schedule changes will be shared with #SCRoadRehab.
For exact street start and end points, please visit the Road Rehab interactive map at santa-clarita.com/RoadRehab. Please note, dates are subject to change and will be updated on the map as soon as possible.